Guide to Using the RIBA Professional Services Contracts 2018 - Other - Page 112
Completing an Agreement
z 111
Letter of amendment to the original PSC after signature
Should the Client make changes which make a material change to the original
Contract, such as advancing the completion date by three months, and the Architect/
Consultant agrees that the practice could resource the accelerated programme
subject to payment of additional fees to cover the high costs of overtime and the
additional risks, the Contract should be confirmed by a variation.
Figure 5.4.7
Letter issuing a formal contract amendment
Dear ……………
Re: PROJECT TITLE
Further to your letter dated
and our subsequent
discussions about the
.
.
As this changes the Agreement between us, it is appropriate to modify that
document by a
.
If you agree that the
correctly expresses your intention,
please
, enter the date where indicated and return one copy to us. Please retain
your copy and keep it with your copy of the Contract.
Should you have any queries then please do not hesitate to contact me.
I look forward to hearing from you.
Yours
,
111