8
What is the aim of Stages 0 and 1?
In the extract from the RIBA Plan of Work 2013 in Figure 1.2 below, the Core
Objectives and Suggested Key Support Tasks of Stages 0 and 1 are set out. The
rationale behind having two stages prior to the commencement of the Concept
Design stage is straightforward: Stage 0 considers strategic issues and Stage 1
adds ‘flesh’ to these strategic bones. The outputs at the end of a successful
Stage 1 would be:
• a robust Initial Project Brief, and
•a collaborative project team.
Stages
These two outputs and the connection between them are considered in detail below.
Tasks
Core
Objectives
Suggested
Key Support
Tasks
0
1
Strategic
Definition
Preparation
and Brief
Identify client’s Business
Case and Strategic Brief
and other core project
requirements.
Develop Project Objectives,
including Quality Objectives
and Project Outcomes,
Sustainability Aspirations,
Project Budget, other
parameters or constraints and
develop the Initial Project Brief.
Undertake Feasibility Studies
and review of Site Information.
Review Feedback from
previous projects.
Prepare Handover Strategy
and Risk Assessments.
Agree Schedule of Services,
Design Responsibility
Matrix and Information
Exchanges and prepare
Project Execution Plan
including Technology and
Communication Strategies
and consideration of Common
Standards to be used.
Figure 1.2 Extract from the RIBA Plan of Work 2013
www.ribaplanofwork.com
= robust
Initial Project
Brief
= collaborative
project team